Method of Estimation
Estimate__
Before undertaking the construction of a project it is necessary
to know its probable cost which is worked out by estimating, an estimating is a
computation or calculation of the quantities required and expenditure likely to
incurred, an estimating is a computation or calculation of the quantities
required and expenditure likely to incurred in the construction of a work . the
primary object of the estimate is to enable one to know beforehand, the cost of
the work (building ,raod,structure ,….etc.), the estimate is probable cost of
work and is determined theoretically by mathematical method of calculation
based on the plans and drawing and current rates. Approximate estimate may be prepared
by various methods but accurate estimate is prepared by detailed
estimate method.
Actual cost
The actual
cost of a work is know as the completion
of the work. Account of all expenditure is maintained day to day during the execution
of work in the account section and at the end of the completion of the work
when the account is completed , the actual cost is know. The actual cost should not differ much from
the estimated cost worked out at he beginning .
Detailed Estimate
Preparation
of detailed estimate consists of working out of quantities of different items
of work and then working out the cost.
The estimate
is prepared in two stages:
1.
Detailed of measurement and
calculation of quantities --- The whole work is divided into different item of the work suck as earthwork,concrete,bricks, block,
substructure work….etc.and the item are classified and grouped under different
sub heads and details of ,measurement of each item of work are taken out
and quantities under each item are
computed in prescribed form. Detailed of measurement form is given below.
2.
Abstract of estimate cost---
the cost under item of work is calculated from the quantities already
computed at workable rate. And the total cost is worked out in a prescribed form,
abstract of estimate form. A percentage of 3 to 5 per cent is added to
contingencies, to allow for petty contingent expenditure , unforeseen
expenditure ,change in design, change in rate.. etc.which may occur during the
execution of work . a percentage of 1 to 2 percent is also added to meet the
expenditure of work- charged establishment . the grand total thus obtained is
the estimated cost of the work. Abstract
of estimate form is given below.
In the above
form the description of each item should be such as to express exactly what
work ,materials ,proportion of mortar….etc have provided for .
In preparing
an estimate item are usually classified and grouped sub –head wise but for
beginner it is continent to make up the item in the same order as far as
possible , as they would be executed or constructed . if the principle of
following the order of construction from foundation to up ward direction is followed
there is little chance of omission of items.
Main items of work
1- Earth work---- earth work is excavation and
earthwork in filling are taken out separately under different item, and
quantities are calculated in cubic meter . foundation trenches are usually dug
to the exact width of foundation with vertical side . earth work in excavation
in foundation is calculated by taking the dimension of each trench width x
length x depth. Filling in trench after the construction of foundation masonry
is ordinary neglected. If the trench filling is accounted this may be
calculated by deducting the masonry from the excavation .
2-
Concrete in foundation ---
the concrete is taken out in cu m by length x breadth x thickness . the length
and breadth of foundation concrete are
usually the same as for excavation.only the thickness and depth is differs. The
thickness of concrete is varies from 20cm to 45 cm, foundation concrete usually
consist of lime concrete or weak cement concrete.
3-
Soling ---- when the soil is soft or bad ,
one layer of dry bricks or stone is applied before the foundation of concrete. The
soiling layer completed in the sq m .
4-
Damp proof course---- D.P.C usually of 2.5cm thick rich
cement concrete 1:1 ½:3 or 2cm .
5-
Masonry ---- Masonry is computed in cu m
length x breath x height. Foundation and plinth masonry is taken under one
item.and masonry in super structure is taken under separate item. In story
building the masonry in each story as ground floor above plinth level, first
floor ,second floor …etc is computed separately .in taking out of quantity the
wall are measured as solid and then deduction are made for opening as
door,window…etc.and such portion are necessary.
DEDUCTION FOR OPENING ,BEARING ETC IN
MASONRY
No deduction
is made for following
1.
Opening each up to 1000 sq cm or 0.1 sq m
2.
End of beams ,posts, rafter,purlins etc upto 500 sq m or
0.05 sq m
3.
Bed plate ,wall plate ,bearing of chajjas and like upto 10 cm depth.
Please click below link for sample
https://theworldpedias.blogspot.com/2022/07/boq-sample-bill-of-quantity.html
Post a Comment